Finish Installing Exterior Building Trim
- Install soffit, fascia and frieze trim around sanctuary roofline, narthex gables, front porch
Finish Laying Brick on All Exterior Walls
- Complete installation of “thin” brick on sanctuary west wall (above music wing)
- Complete finish brick on west and south walls of expanded music wing
- Weather permitting, clean all brick
Continue Rough Framing in Sanctuary
- Soffit and light cove inside column line on either side of sanctuary
- HVAC attic space outside column line on either side of sanctuary
- Finished “barrel” ceiling the entire length of sanctuary
Continue Electrical Work in Sanctuary and Town Square
- Continue electrical installations, primarily throughout sanctuary and town square
Continue HVAC Duct Work in Sanctuary and Lower Level
Begin Instllation of Fire Suppression Lines in Sanctuary
- Install piping below fire ceiling and above finished “barrel” ceiling
Continue Installing Drywall in Lower Level Rooms
- Install drywall over insulation on all interior walls
- Tape, mud and sand all drywall