Construction Updates

The latest information on the Sacred Space Construction

What’s New This Week? 07-16-21 to 07-31-21

Work continues in the lower level, building block walls and completing the drainage system.

Plumbers Construct Underground Drainage.

With foundation walls in place, plumbers begin installing a new underground drain system.

Masons Build Block Walls in Lower Level.

A team of masons has started construction of block walls in the new lower level.

What’s New This Week? 07-01-21 to 07-15-21

Despite rain, foundation wall work completed, for now.

Record Rain Does Not Deter Progress.

Rain, rain, go away, come again some other day.

Foundation Walls Rise from Solid Footings.

Construction of foundation walls for the new sanctuary is well underway.

What’s New This Week? 06-16-21 to 06-30-21

Footings and pads complete as foundation walls about to be poured.

The Church’s One Foundation …

The day after groundbreaking ceremonies work began in earnest laying the church’s new foundation.

What’s New This Week? 06-01-21 to 06-15-21

Excavation work almost complete as activity begins to focus on foundation installation in June.