The following work is scheduled for 03-01-21 to 03-15-21, including work on the office wing renovation and  …
Read More
Work has started on the office renovation.  The ministry team has relocated temporarily to the Library.  Demolition is complete, the new office walls have been constructed and electrical work is underway.  In addition to wiring the newly renovated offices, the 1950’s electrical service in the office wing is being updated and upgraded.
Read More
The following work is scheduled for 2-15-21 to 2-28-21: Receive construction permit from the City of Birmingham Finalize ‘site logistics plan’ Setup construction trailer & COVID check-in station Remove select trees Install construction fence & signage Church staff packs and moves offices to temporary library location Complete preparation for Columbarium transfer to Redeemer Chapel Preparation...