What’s New This Week? 03-01-15 to 03-15-21

What's Happening March 1 - 15, 2021?

The latest construction updates.
  • Begin renovation of office wing
    • Build interior construction (safety) walls.
    • Demolition of select interior walls and doors.
    • Rough electrical (re)location.
    • Heating and Cooling.
    • Masonry infill, lintels, openings.
    • Construction of new office walls (drywall, etc.).
    • Rough plumbing for new bathrooms.
    • Extend fire suppression throughout office wing.
  • Interior preparation for demolition
    • Complete relocation of all worship aids to gymnasium
    • Remove and pack chandelier for reuse in new sanctuary
    • Prepare for interior asbestos remediation
    • Selective interior plumbing/electrical demolition
  • Exterior preparation for demolition
    • Disassembly and storage of columbarium components
    • Sanitary / Storm Water / Water Main work
    • Removal and storage of benches, lamp posts, etc.

Construction Gallery