On Sunday, April 10, 2022, construction tours will be offered after the 9:00 a.m. and 10:30 a.m. worship services. Come see our progress firsthand!
Weather allowed some work to continue on the Redeemer exterior during the second half of March.
The interior of the sanctuary has seen a great deal of activity.
The lower level is ahead of the pace upstairs in the sanctuary. All drywall has received final paint colors. The various teams have moved on to finish work.
Complete Framing and Drywall in Town Square and Narthex Ceiling
Continue Finish Carpentry Work
Continue Finish Electrical Work in Sanctuary
Continue HVAC Work in Sanctuary and Lower Level
Complete Tile Installation in All Lower-level Bathrooms
Complete Exterior Fascia, Gutter and Downspout Work
Continue Relocation Work for New Columbarium