Progress on the relocated columbarium highlights the work on the Redeemer exterior:
The interior of the sanctuary has seen a great deal of activity, most notably the installation of tile in the sanctuary:
The lower level (classrooms, fellowship hall, bathrooms, bridal lounge, etc.) are nearing completion:
Continue Finish Carpentry Work in Tandem with Painters
Continue Installing Floor Tile in Sanctuary
Complete Ceiling Grids for Drop-in Acoustic Tile
Continue Finish Electrical Work Inside and Outside Sanctuary
Continue Mechanical Work Inside and Outside Sanctuary
Complete Fixture Installation and Connection in All Lower-level Bathrooms
Complete Exterior EIFS, Fascia, Gutter and Downspout Work
Continue Relocation Work for New Columbarium