The majority of the work on the Redeemer exterior in late May focused on the columbarium:
The interior of the sanctuary has seen a dramatic change with the completed installation of tile throughout the sanctuary and narthex, as well as the balcony:
The lower-level spaces (classrooms, fellowship hall, bathrooms, bridal lounge, etc.) are nearing completion:
Complete Finish Carpentry Work in Tandem with Painters
Complete Ceiling Grids for Drop-in Acoustic Tile (music wing and town square)
Complete Finish Electrical Work Inside and Outside Sanctuary
Complete Exterior EIFS, Fascia Work
Complete Relocation Work for New Columbarium
Complete Excavation and Rough Grade for Parking Lot Curbs and All Sidewalks
Pour All Remaining Steps and Sidewalks in Preparation for Landscaping