The music wing, which sits immediately west of the sanctuary, is being expanded. Work began on this phase of the project over the past two weeks. The expanded space will include:
The initial work involved pouring steel reinforced foundations to support steel reinforced block walls. The foundations have all been poured and work has begun on the block walls. The new wall that is visible on construction cam #2 is an interior hallway that leads from outside, through the middle of the expanded music wing, to the sanctuary. Masons will complete the remaining block walls over the second half of October. Work will then proceed in parallel with the sanctuary, including roof trusses and a finished roof.