A week of good weather has allowed good progress as the new church structure rises from the ground.
New video footage (below) shows the steel from above, via a drone flyover, and from below, inside the new lower level. Ironworkers have been busy bolting and welding each joint throughout the lower level. The steel columns and beams will support the pre-cast concrete planks that will be installed later this month. The ironworkers will return at a later date to install the sanctuary balcony structure and two lower level stairways.
The photos below also capture the recently installed gravel floor in the lower level. The gravel covers the drainage, sanitary plumbing and electrical conduits that run throughout the lower level. After the remaining foundation wall is poured next week, the same contractor that laid the gravel will return to pour the new concrete basement floor.