The construction camera clearly shows a sanctuary ceiling. But this drywall, installed just below the roof truss insulation, is only a fire layer. The final, barrel shaped ceiling, has yet to be installed. For the carpenters to complete the ceiling, other trades are working to complete important steps. Namely, the installation of the sanctuary fire supression system, the installation of HVAC ducts and the installation of all power, data and audio visual conduits.
Framing of the ceiling is well underway. A light cove that runs the length of the sanctuary, on both sides, has already been installed. Soffits, below the light cove, and above the windows, are currently being framed. These large soffits conceal the HVAC ducts that run from front to back. With this work complete, the carpenters will install a curved ceiling (44′ radius) that disappears in to the light cove on each side of the sanctuary.
The final installation of the barrel ceiling requires other important steps to be completed: