Masons have now built all the block walls for the new sanctuary and music wing expansion. Only a small gable on the south end of the music wing remains to be built with block. As such, the same team of masons will now turn their attention to laying the “Redeemer” red brick around the sanctuary. This brick work has just begun on the west wall of the sanctuary (see construction cam #2.) The block walls were first sprayed with an insulating foam. The finish bricks are then laid with a roughly 2″ air pocket between the brick and insulating foam. The detailed brick work around the sanctuary windows is just begining to take shape (see gallery photos below.)
In addition to the masons, the carpenters are continuing to frame interior rooms with metal stud and metal door frames. The work in the lower level (children’s classrooms, fellowship hall, resource center, bridal lounge, bathrooms and storage rooms) is nearly complete. They will then turn their attention to rooms on the main level (town square, sacristy, chancel, music wing, storage rooms.) Some of this main level work will not be completed until the roof trusses are installed. The trusses are currently being fabricated and as such there is no firm date on their delivery and installation.
Other notable accomplishments these past two weeks include:
Complete Block Walls and Gable for Music Wing Expansion
Begin Laying Finish Brick on All Exterior Walls
Complete Spray Insulation on All Exterior Block Walls
Continue Electrical Work on Main Level
Continue Installation of Metal Studs for Interior Rooms
Install HVAC Duct Work in Lower Level