Installation of the new steeple on Thursday, April 21, 2022, was a major milestone over the past two weeks. But less visible work was accomplished inside and outside the new sanctuary.
Key milestones around the Redeemer exterior included:
The interior of the sanctuary has seen a great deal of activity, with trades wrapping up work in some cases:
The lower level (classrooms, fellowship hall, bathrooms, bridal lounge, etc.) saw multiple teams at work:
Continue Finish Carpentry Work in Tandem with Painters
Begin Installing Floor Tile in Sanctuary Beginning with the Chancel
Complete Ceiling Grids for Drop-in Acoustic Tile
Continue Finish Electrical Work Inside and Outside Sanctuary
Continue Mechanical Work Inside and Outside Sanctuary
Complete Fixture Installation in All Lower-level Bathrooms
Complete Exterior EIFS, Fascia, Gutter and Downspout Work
Continue Relocation Work for New Columbarium